Tugasan 4

Assignment 4:  USE YOUR KNOWLEDGE TO COMPUTE THE ECONOMIC FEASIBILITY OF THE CASE BELOW


1.         Consider the information given below AND ANSWER the questions following it:
                                                                                                           
Development Costs
Hardware                    RM 20,000
Software                     RM 10,000
Training                       RM   8,000

Annual Production Cost
Supplies                       RM   1,500
IS personnel                RM 30,000 in year 1;    10% annual increase
Maintenance                RM   3,000 per year

Expected Annual Benefits

Labor savings              RM 20,000 in year 1;   5% increase annually
Increase sales              RM 25,000 in year 1;   10% increase annually


Assumptions:
Discount rate                           15 %
Sensitivity factor (cost)           0.5
Sensitivity factor (benefit)      0.9



Questions:
  1. Create a cost-benefit analysis table (for 4 years) to assess the economic feasibility of the proposed system.





  1. What is the profitability index computed for this project?
           (Gain/Loss) / Dev Cost = -0.4680 > NOT Feasible!!!

  1. Do you recommend that the organization fund this development project? Why and why not?
          No, because company will loss all the investment and profit.