1. Using
Microsoft Project create a Network diagram for the activity below. What is the
critical path ?
Gantt chart
Network diagram
The critical path are determine by the red box and the total days for critical path are 18 days
2.A
diagram below represents the Interviewing Activities. Draw the Network diagram and
determine its critical path.
Gantt chart
Network diagram
The critical path are determine by the red box and the total days for critical path are 12 days