Tugasan 2

Enter the activities below and produce the Gantt chart.


TASK/ACTIVITIES                                                             DURATION

1.    PLANNING Phase
                                                       
Select group members                                                        1 day
Define problem                                                                    1 day
Produce Project schedule                                                   1 day
Calculate project feasibility                                                  1 day 
                                                                                                       ---------  
2.    ANALYSIS Phase
                                                       
Gather information                                                              3 days
Define Systems Requirements                                           3days
Write the proposal Document                                             3 day
Send proposal Document                                                   0 day
Draw logical DFD                                                                3 days
                                                                                             --------  
3.    DESIGN Phase
                                                                   
Design current  process                                                     3 days
Design new process                                                           5 days
Design Data Base                                                               5 days
Design Interface and forms                                                 5 days
Send Design Documents                                                    0 day
                                                                                                       --------  
4.    IMPLEMENTATION PHASE

Do Coding                                                                             8 days
Do testing                                                                              3 days
Do Acceptance Test                                                              2 day
Write Report Document                                                         5 days
Do Final Class Presentation                                                  0
                                                                                                          -------- 

                TOTAL NO. OF DAYS (PROJECT DURATION TIME )          52 days    


    